2019
April - Workshop with Oxford Design Review Panel (ODRP) - Complete
May - Public Consultation event 1 - Complete
September - Planning approval for demolition and enabling works application granted - Complete
December - Start of demolition works - Complete
2020
May - Oxford Design Review Panel Full Review - Complete
June - Public Consultation event 2 - Complete
October - Submission of planning application - Complete
December - Completion of demolition works - Complete
2021
January - Planning consent granted - Complete
June - Proposed commencement of works on new building
2024
September - Opening of new building